What 9 companies say they will deliver by October 2028

9 dated commitments, 9 of them order delivery windows. Every line carries the words the date was read out of, and the filing it came from.

4 of these are marked ≈ — the company counted from a date it did not give, such as “18 months from the appointed date”, so River resolved it from the filing date and says so rather than presenting an estimate as a stated date.

None of these has come due yet. River will not tell you whether they will be met; it tells you what was said, and when.

J.Kumar Infraprojects Limitedorder₹ 2,360,00,00,000/1 Oct 2028

Village on NH 48 (Design length=32.180 Km) under NH (O) in the State of Maharashtra on EPC Mode, for the total contract cost amounting to ₹ 2,360,00,00,000/‐ (Rupees Two

said 1 Apr 2026 · from the words “30 (Thirty) Months” · for National Highways Authority of India · source filing

EMS LimitedorderRs. 12,980.13 lakhs8 Oct 2028

The estimated order value (including GST but excluding O&M) is Rs. 12,980.13 lakhs (Rupees Twelve Thousand Nine Hundred and Eighty Lakhs Only).

said 8 Oct 2026 · from the words “24 months” · for Municipal Corporation Jodhpur · source filing

Ashoka Buildcon Limitedorder≈ 9 Oct 2028

Further to apprise that the Company has received Letter of Acceptance for the said Project.

said 9 Oct 2026 · from the words “Completion Period: 24 months from date of commencement” · for North Eastern Railway · source filing

Railtel Corporation Of India Limitedorder11 Oct 2028

Development of Integrated Environment & Housekeeping Management (EnHM) Digital Platform of Indian Railway &#65533. Awarded by MinistryOfRailwaysRailBhavan

said 9 Oct 2026 · from the words “11-OCT-28” · for Ministry Of Railways Rail Bhavan · source filing

Glass Wall Systems (India) LimitedorderINR 50 crore≈ 15 Oct 2028

Upto INR 50 crore Above INR 50 crore and Above INR 100 crore

said 15 Oct 2026 · from the words “Project Delivery Schedule: 24 Months from order effective date” · for Indian Company · source filing

GPT Infraprojects Limitedorder₹ 149.50 Crore≈ 15 Oct 2028

GPTINFRA Bags Order Valued at ₹ 149.50 Crore

said 16 Oct 2026 · from the words “730 Days from Appointed Date” · for CSTE, Western Railway, Bhavnagar Division · source filing

Vascon Engineers LimitedorderRS. 198 CRORE16 Oct 2028

EPC Mode. Awarded by State Bank of India, Premises and Estate Department, Maharashtra Circle, Pune- 411014

said 16 Oct 2026 · from the words “work has to be completed within 24 months” · for State Bank of India · source filing

Power Mech Projects Limitedorder₹ 227.95 Crores≈ 27 Oct 2028

We are pleased to inform you that the Company has secured an order from SOUTH WESTERN RAILWAY, BANGALORE.

said 27 Apr 2026 · from the words “within 30 months from the Appointed Date” · for SOUTH WESTERN RAILWAY, BANGALORE · source filing

Avantel LimitedorderRs.12.04 Cr31 Oct 2028

No. 49, Block - 1, Vasavi’s Shalom Sky City, Gambheeram (V), Anandapuram (M), E-City, Raviryal (V), Maheswaram (M), Gachibowli, Serilingampally (M), Ranga Reddy (D), Visakhapatnam - 531 163, Andhra Pradesh.

said 10 Oct 2026 · from the words “October 2028” · for Larsen & Toubro Limited · source filing

Other months

2028-10 · 2028-09 · 2028-08 · 2028-07 · 2028-06 · 2028-05 · 2028-04 · 2028-03 · 2028-02 · 2028-01 · 2027-12 · 2027-11 · 2027-10 · 2027-09 · 2027-08 · 2027-07 · 2027-06 · 2027-05 · 2027-04 · 2027-03 · 2027-02 · 2027-01 · 2026-12 · 2026-11 · 2026-10 · 2026-09 · 2026-08 · 2026-07 · 2026-06 · 2026-05 · 2026-04 · 2026-03

This month as JSON · every stated date

A date passing is not news anyone reports.

One email a week: what came due, what was filed after, and what is next — with the filing linked on every line.