What 13 companies say they will deliver by May 2028

17 dated commitments, 10 of them order delivery windows and 7 from management’s own statements. Every line carries the words the date was read out of, and the filing it came from.

1 of these are marked ≈ — the company counted from a date it did not give, such as “18 months from the appointed date”, so River resolved it from the filing date and says so rather than presenting an estimate as a stated date.

None of these has come due yet. River will not tell you whether they will be met; it tells you what was said, and when.

Enviro Infra Engineers Limitedorder₹ 113.51 Crore1 May 2028

The Company has received the official communication from the Department on 01st May, 2026 at 01:48 P.M. (IST).

said 1 May 2026 · from the words “within 24 months” · for Sardar Sarovar Narmada Nigam Limited · source filing

EMS LimitedorderRs. 14379.53 lakhs4 May 2028

The Estimated order value (excluding GST) is approximately Rs. 14379.53 lakhs (Rupees Fourteen Thousand Three Hundred and Seventy-Nine Lakhs Only).

said 4 May 2026 · from the words “24 months” · for UP Jal Nigam · source filing

Dev Information Technology Limitedorder₹2.79 Crores7 May 2028

The total project value is approximately ₹2.79 Crores (excluding GST), with defined timelines for website and digital twin development and an AMC support period post go‑live to ensure continuous operation and enhancements

said 7 May 2026 · from the words “to be executed;– Approximately 2 Years” · for Gujarat International Finance Tec · source filing

PNC Infratech LimitedorderRs. 194.4 Crores7 May 2028

Uttar Pradesh for a quoted orice of Rs. 194.4 Crores

said 7 May 2026 · from the words “24 Months” · source filing

PNGSREVAsaid14 May 2028

we have mentioned in DRHP, RHP prospectus that this is a project for 24 months' period.

said 14 May 2026 · from the words “24 months”

PNGSREVAsaid14 May 2028

I expect top-line growth also to get maintained around 25% to 30%.

said 14 May 2026 · from the words “next two years”

RATNAVEERsaid14 May 2028

2 Years ₹750+ Cr * 22% 15%

said 14 May 2026 · from the words “2 Years”

Marine Electricals (India) LimitedorderRs 208.72 crores18 May 2028

We are pleased to inform you that Marine Electricals (India) Limited has received orders amounting to total of Rs 208.72 crores Excluding Taxes, the details of the same are mentioned as under: 1.

said 18 May 2026 · from the words “over a period of 24 months” · source filing

IKSsaid20 May 2028

think of it as a good, still a good two-year type product journey

said 20 May 2026 · from the words “two years”

RATNAVEERsaid21 May 2028

parallel, that CCL business can be established in the next 2 years. That can be given the 750 crores as a top line

said 21 May 2026 · from the words “next 2 years”

RATNAVEERsaid21 May 2028

remaining four lines all together, or we can be split out the two lines, of each year, so maximum over the two years of the time, we can install all the four or five lines together

said 21 May 2026 · from the words “next 2 years”

Dilip Buildcon LimitedorderRs. 268 Crores22 May 2028

Engineering, Procurement and Construction (EPC) Work for Designing and Construction of Ged Barrage, Protection work & Other allied activities across Sabarmati R. Awarded by Narmada Water Resources Water Supply & Kalpasar Department, Government of Gujarat

said 22 May 2026 · from the words “24 Months” · for Narmada Water Resources Water Supply & Kalpasar Department · source filing

GPT Infraprojects Limitedorder₹ 72 Crore≈ 25 May 2028

GPTINFRA Bags Order Valued at ₹ 72 Crore

said 26 May 2026 · from the words “730 days from the Appointed Date” · for PCMM, Eastern Railway · source filing

YATHARTHsaid25 May 2028

Bed capacity to be expanded by 200 and 250 beds at Greater Noida & Noida Extension

said 25 May 2026 · from the words “over next 24 months”

Sadhana Nitrochem LimitedorderRs. 108 crores28 May 2028

The contract b) order/contract awarded in brief has a firm committed aggregate value of approximately Rs. 108 crores over a period of two years.

said 28 May 2026 · from the words “Two years” · source filing

PNC Infratech LimitedorderRs.302.44 Crore29 May 2028

NAV-AIDS Facilities, Perimeter Road, Approach Road, Runway Lighting System, allied works etc.) at Pantnagar Airport in Uttarakhand on EPC Basis" on29.5.2026 for a quoted price of Rs.302.44 Crore (Rupees Three Hundred Two Crore and Forty-Four Lakhs only) excluding GST.

said 29 May 2026 · from the words “24 Months” · source filing

Mtar Technologies LimitedorderRs 126.74 Cr31 May 2028

Regulations, 2018 - for receipt of Purchase orders worth Rs 126.74 Cr.

said 26 Aug 2026 · from the words “26th May, 2028” · for Nuclear Power Corporation of India Limited · source filing

Other months

2028-10 · 2028-09 · 2028-08 · 2028-07 · 2028-06 · 2028-05 · 2028-04 · 2028-03 · 2028-02 · 2028-01 · 2027-12 · 2027-11 · 2027-10 · 2027-09 · 2027-08 · 2027-07 · 2027-06 · 2027-05 · 2027-04 · 2027-03 · 2027-02 · 2027-01 · 2026-12 · 2026-11 · 2026-10 · 2026-09 · 2026-08 · 2026-07 · 2026-06 · 2026-05 · 2026-04 · 2026-03

This month as JSON · every stated date

A date passing is not news anyone reports.

One email a week: what came due, what was filed after, and what is next — with the filing linked on every line.