The Clock · September 2027
What 28 companies say they will deliver by September 2027
35 dated commitments, 32 of them order delivery windows and 3 from management’s own statements. Every line carries the words the date was read out of, and the filing it came from.
3 of these are marked ≈ — the company counted from a date it did not give, such as “18 months from the appointed date”, so River resolved it from the filing date and says so rather than presenting an estimate as a stated date.
None of these has come due yet. River will not tell you whether they will be met; it tells you what was said, and when.
Engagement of user fee agency on the basis of competitive bidding at Mangapatnam Fee Plaza at Tadipatri to Jammalamadugu via Muddanur of NH-67 in the state of Andhra Pradesh and upkeep/maintenance of adjacent
said 3 Sep 2026 · from the words “1 year” · for NHAI (National Highways Authority of India) · source filing
430+380, along with Approaches and Service Roads near college square and DRDA square in Puintola to Icchapuram section of NH-16 in state of Odisha on EPC mode.
said 4 Mar 2026 · from the words “18 Months” · for National Highways Authority of India · source filing
Signaling & Telecom arrangements in connection with yard remodeling of Guntur Junction and Automatic Block Signaling System between GNT-NLPD Section in GunturDi. Awarded by Dy.Cste/Projects/Bza
said 14 Mar 2026 · from the words “04-SEP-27” · source filing
Sigma-, Corporales, corporate House No, Sindhu Bhavan Road Nr ~,'ann Party Plot Cross Road Bodakdev A,hmedabad ' J80 054, GUjarat India, Te'efax : +91 - 7G
said 5 Mar 2026 · from the words “18 months” · for Dakshin Gujarat Vij Co. Ltd · source filing
Nature of order(s) / contract(s) Comprehensive Signalling and Telecommunication Works for Provision of Automatic Block Signalling System. Awarded by South Central Railway
said 15 May 2026 · from the words “within 480 days from the Appointed Date” · for South Central Railway · source filing
Engagement of user fee collection agency on the basis of competitive bidding though E-Tender for Pachwara fee plaza of NH-39 for four laning of Jhansi Khajuraho Section in the state of Madhya Pradesh and upkeep/maintenance of adjacent toilet blocks including recouping the consumable items
said 8 Sep 2026 · from the words “1 year” · for NHAI (National Highways Authority of India) · source filing
The estimated order value of the Work awarded (excluding TCS) is approximately Rs. 2,838.88 lakhs (Rupees Two Thousand Eight Hundred and Thirty-Eight Lakhs Only).
said 9 Sep 2026 · from the words “1 Year” · for National Highways Authority of India · source filing
Paras Defence and Space Technologies Limited (“PARAS”), has received an order from DRDO, Ministry of Defence valued at approximately Rs. 80.28 Cr.
said 9 Mar 2026 · from the words “Execution within 18 Months from the Date of Supply Order” · for DRDO, Ministry of Defence · source filing
Station buildings), and P-way works for BOQ development of Railway Infrastructure at 2x800
said 10 Mar 2026 · from the words “18 months” · for Anuppur Thermal Energy (MP) Private Limited · source filing
GPTINFRA Bags Order Valued at ₹ 85.53 Crore
said 12 Sep 2026 · from the words “12 months from LOA” · for CSTE Con, Eastern Railway, Kolkata · source filing
VA TECH WABAG (‘WABAG’), a leading pure-play water technology Indian multinational group, has secured a Letter of Award (‘LoA’) from the Chennai Metropolitan Water Supply and Sewerage Board (‘CMWSSB’) for the Refurbishment, Finance, Operate, Maintain and Transfer (‘RFOMT’) of a 45 Million Litres per Day (‘MLD’)…
said 12 Mar 2026 · from the words “within a period of 18 months” · for Chennai Metropolitan Water Supply and Sewerage Board (‘CMWSSB’) · source filing
“Construction of Diversion Road from 4/700 km to 11/500 km of Duduka-Gopalpur-Toparia Road (6 Lane with Service Road) in the District of Sundargarh on EPC Mode". Awarded by Odisha Bridge & Construction Corporation Limited (OBCCL)
said 14 Mar 2026 · from the words “18 Months” · for Odisha Bridge & Construction Corporation Limited (OBCCL) · source filing
Up to Rs.100 Cr Rs. 100 Cr to Rs. 500 Cr Rs. 500 Cr to Rs.1000 Cr Rs.1000 Cr and above The Company is committed to delivering high-quality products and services and has established itself as a leading manufacturer of transformers in the country over time.
said 14 Aug 2026 · from the words “Scheduled of delivery within next 13 Months” · for APTRANSCO · source filing
The contract value is Rs. 6,58,35,987 including GST.
said 12 Sep 2026 · from the words “1 year from September 16, 2026 to September 15, 2027” · for Maha Mumbai Metro (M3) Operation Corporation Limited · source filing
The contract value is Rs. 20,64,385.00/- (Rupees Twenty Lakh Sixty-Four Thousand Three Hundred and Eighty-Five Only) plus 18% GST amounting to Rs. 3,71,589.30/- (Three Lakh Seventy-One Thousand Five Hundred and Eighty-Nine and Thirty Paise Only) = Total contract value is Rs.
said 16 Sep 2026 · from the words “work shall be completed within 12 months” · for Larsen & Toubro Limited, Construction · source filing
The total value of the contract is THB 10,542,056.07 (approximately Rs. 3 crore), exclusive of applicable taxes.
said 10 Jul 2026 · from the words “15 months (from June 24, 2026 to September 20, 2027)” · for Krung Thai Bank Public Company Limited (KTB), Thailand · source filing
15+100 of Ambala – Chandigarh section of NH205A and terminating at Ch.
said 20 Mar 2026 · from the words “18 Month Construction Period & 15 Year Operation & Maintenance Period” · for National Highways Authority of India · source filing
Corporate Identification No.: U45201DL2003PLC120995 (Formerly Known as " Annu Projects Private Limited")
said 22 Sep 2026 · from the words “to be executed 12 months” · for EAST CENTRAL RLY DRM Office · source filing
Nature of order(s) / contract(s) Replacement of panel Interlocking with
said 31 Mar 2026 · from the words “Within 540 days from the Appointed Date as per EPC Agreement Document” · source filing
Bagging/Receiving of orders/contracts — ARSS Infrastructure Projects Limited has informed the Exchange about Bagging/Receiving of orders/contracts
said 23 Oct 2026 · from the words “11 (Eleven) Months” · source filing
Rs. 3,72,38,087/- (Thirty-seven million, two
said 23 Jun 2026 · from the words “15 Months” · for Ajmer Vidyut Vitran Nigam Limited · source filing
Energy MH1 Limited & Ceigall Green Energy MH2 Limited, wholly owned subsidiaries of Ceigall
said 25 Mar 2026 · from the words “• 18 Months of Work Execution • 25 Years of Operational Period” · for Maharashtra State Electricity Distribution Co. Ltd · source filing
Pace Digitek Limited (Formerly Known as Pace Digitek Private Limited and Pace Digitek Infra Private Limited)
said 26 Mar 2026 · from the words “Within 18 months” · for North Western Railway · source filing
Ceigall India Limited Wins Rs 603-Crore NHAI Contract for 6-Lane Spur Project in Punjab New Delhi, March 27, 2026: Ceigall Infra Projects Private Limited (CIPPL), a wholly owned subsidiary of Ceigall India Limited (‘CIL’), has received a Letter of Award (LOA) from the National Highways Authority of India (NHAI) for…
said 27 Mar 2026 · from the words “18 Month Construction Period & 15 Year Operation & Maintenance Period” · for National Highways Authority of India · source filing
The complete payload shall qualify as a Space-Borne System having potential utilisation for Earth Observation.
said 28 Sep 2026 · from the words “delivery date is on or before 27 September 2027” · for DRDO, Ministry of Defence · source filing
EPC Package for supply, services and Annual Maintenance for BESS Implementation at Kudgi Super Thermal Power Station and Ramagundam Super Thermal Power Station. Awarded by NTPC Limited
said 28 Mar 2026 · from the words “within 18 months” · for NTPC Limited · source filing
Order worth approx. ₹2,025 crore for 500 MW / 550 MWp Solar EPC Project from NACOF
said 29 Sep 2026 · from the words “within 12 Months” · for NACOF Oorja Private Limited (“NOPL”), a subsidiary of NACOF · source filing
Supply of up to 30 units of EVOQ360 Home Lifts. Awarded by Gulf Elevators Private Limited
said 13 Oct 2026 · from the words “On or before September 30, 2027” · for Gulf Elevators Private Limited · source filing
Storage Systems (BESS) in Gujarat of Gujarat Urja Vikas Nigam Limited(GUVNL) under Tariff-Based competitive bidding (Phase-VIII) with Viability Gap Funding supported through PSDF followed by ERA.
said 31 Mar 2026 · from the words “18 Months from date of Battery Energy Storage Purchase Agreement” · for Gujarat Urja Vikas Nigam Limited (GUVNL) · source filing
The total value of the said order is Rs.137.12 Crores (Rupees One Hundred Thirty-Seven Crore and Twelve Lakh Only), exclusive of taxes.
said 28 Mar 2026 · from the words “September 2027” · for India Meteorological Department (IMD) · source filing
within a year, by maybe next August, September, hopefully we should have the plant for this
said 21 May 2026 · from the words “August-September 2027”
The approximate contract value is Rs. 6.60 Crore excluding all applicable taxes.
said 27 Aug 2026 · from the words “12 (Twelve) Months from October 01, 2026 to September 30, 2027” · for Shree Shyam Mandir Committee · source filing
Paras Defence and Space Technologies Limited (“PARAS”), has received an order from Bharat
said 2 Jun 2026 · from the words “Execution to be completed on or before September 2027” · for Bharat Electronics Limited · source filing
we have time till September end 2027
said 22 May 2026 · from the words “by September 2027”
we currently expect 5,500 metric tons annual capacity facility to be completed by Q2 FY27-'28
said 29 May 2026 · from the words “Q2 FY28”
A date passing is not news anyone reports.