What 41 companies said they would deliver by September 2026
60 dated commitments, 24 of them order delivery windows and 36 from management’s own statements. Every line carries the words the date was read out of, and the filing it came from.
1 of these are marked ≈ — the company counted from a date it did not give, such as “18 months from the appointed date”, so River resolved it from the filing date and says so rather than presenting an estimate as a stated date.
These dates have passed. Whether the work was done is not on this record — a listed company must disclose winning an order, and amending or terminating one, but is not required to disclose completing one.
Oswal Pumps Limited is pleased to announce that it has received an additional order from Maharashtra State Electricity Distribution Company Limited (MSEDCL) under the PM Kusum B Scheme “Magel Tyala Saur Krishi Pump” Yojna for the supply and installation of 10,000 OffGrid Solar Photovoltaic Water Pumping Systems, with…
said 4 Jul 2026 · from the words “within 60 days” · for Maharashtra State Electricity Distribution Company Limited · source filing
Regulations, 2015, read with Para B of Part A of Schedule III thereto, we wish to inform you that the Company has received a Letter of Acceptance (LoA) from Steel Authority of India Limited (SAIL) – IISCO Steel Plant (ISP), Burnpur.
said 5 Aug 2026 · from the words “within 30 days” · for Steel Authority of India Limited - IISCO Steel Plant (ISP), Burnpur · source filing
Further to the intimation dated July 2, 2026, regarding receipt of a Letter of Empanelment and Rate Contract, the Company has received an additional allocation under the aforesaid contract.
said 8 Jul 2026 · from the words “Within 60 days” · for Maharashtra State Electricity Distribution Company Limited (MSEDCL) · source filing
Promoter Group / group companies have any interest in the entity that awarded the order / contract.
said 9 Jun 2026 · from the words “3 Months” · for Meet Synthetics Private Limited · source filing
Diamond Power Infrastructure Ltd (DICABS) receives Medium Voltage cable orders worth ₹195.48 crore from Rajesh Power Services Ltd for PGVCL’s disaster-resilience and urban underground projects in coastal Gujarat
said 11 Aug 2026 · from the words “within 30 days” · for Rajesh Power Services Limited, Ahmedabad ("RPSL"), an EPC · source filing
Further, we hereby confirm that none of the promoters/promoter group have any interest in the entity/entities from whom the order/contract is received and the award of order does not fall within the purview of related party transactions.
said 10 Mar 2026 · from the words “6 months” · for Siemens Financial Services Private Limited · source filing
We are pleased to announce that Marine Electricals (India) Limited has received orders totaling Rs. 27.21 crores (excluding taxes) from Princeton Digital Group (India) Management Private Limited.
said 10 Mar 2026 · from the words “over a period of 6 months” · for Princeton Digital Group · source filing
Nature of order(s) / contract(s) Supply of One BTAP Rake and One Break. Awarded by Hindalco Industries Limited
said 12 Apr 2026 · from the words “Order will be executed within 5 months from the date of the PO” · for Hindalco Industries Limited · source filing
Supply Order. Awarded by Directorate General, Sashastra Seema Bal (SSB) Ministry of Home Affairs, Government of India
said 17 Mar 2026 · from the words “180 days from the Date of issue of Letter of Award (LOA)” · source filing
Supply, Installation, Testing & Commissioning of 6 KVA Single phase input & Single phase out put online UPS at 3,000 numbers Sub Center, 336 Urban Health and We. Awarded by West Bengal Medical Services Corporation (WBMSC), Kolkata
said 17 Mar 2026 · from the words “180 days” · for West Bengal Medical Services Corporation (WBMSC), Kolkata · source filing
within a month, we will be ready with our protocols. Yet, it is not decided as you asked me about the about how and what has to be done, but yes, after a month, I think we will be ready with our protocols and it will be published for sure.
said 14 Aug 2026 · from the words “within one month”
Order value (excluding GST) Rs. 1,61,85,000/- GST Rs. 29,13,300/- Total value (including GST) Rs. 1,90,98,300/- The order is to be executed within 15 days in accordance with the agreed terms of the Purchase Order.
said 31 Aug 2026 · from the words “Within 15 days” · for 3C IT Solutions & Telecoms (India) Limited · source filing
Rs. 18,33,30,691/- [Eighteen Crore Thirty-Three Lakh Thirty Thousand Six Hundred Ninety-One
said 4 Aug 2026 · from the words “to be executed period of 45 days” · for PASCHIM GUJARAT VIJ COMPANY LTD · source filing
WorkOrder. Awarded by DepartmentOfPosts
said 10 Aug 2026 · from the words “21-SEP-26” · for Department Of Posts · source filing
Nature of order(s) / contract(s) Reliability improvement of Track circuits. Awarded by North Central Railway
said 29 Mar 2026 · from the words “entire work shall be completed within 180 days” · for North Central Railway · source filing
This order book is expected to be executed in next three-four months.
said 27 May 2026 · from the words “next three-four months”
Warranty Bank Guarantee equal to 10% of the Total Contract Price (including taxes and duties) within 45 days of signing of Contract.
said 14 Aug 2026 · from the words “within 45 days” · for Indian Army, Ministry of Defence, Government of India · source filing
Broad commercial consideration or size of the The order is valued at ₹226.35 Crores (exclusive Order/Contract of G.S.T).
said 28 Mar 2026 · from the words “to be executed 6 months” · for JSW Port Logistics Private Limited · source filing
that product is already almost towards the end of completion, should be commercialized by the end of this quarter or latest by the start of next quarter
said 30 Jul 2026 · from the words “Q2 FY27”
the unpledging process would take another couple of months. So, hopefully by the half year ending, we should have zero pledge in Annapurna.
said 26 Aug 2026 · from the words “by September 2026”
Intimation of Receipt of Letter of Intent for the order
said 19 Jun 2026 · from the words “Upto September, 2026” · for JfE Shoji India Private Limited · source filing
In Q2, we should not see a material degradation from RM any further.
said 7 Aug 2026 · from the words “Q2 FY2027”
Start of Production at Hosur in Q2, FY27
said 3 Aug 2026 · from the words “Q2 FY27”
Further, an amendment to the Purchase Order has received on May 21, 2026, for the supply of Power Amplifiers, adding an additional order value of Rs.1.92 Crores over and above the existing order value of Rs.11.04 Crores.
said 22 May 2026 · from the words “September 2026” · for Bharat Electronics Limited · source filing
Some of these deals are likely to just kind of culminate in a couple of months.
said 30 Jul 2026 · from the words “next two months”
Rs 4,07,12,250.00 (Rupees Four Crore Seven Lakh Twelve Thousand Two Hundred Fifty
said 30 May 2026 · from the words “4 Months” · for Emotiv Mobility, LLC, USA · source filing
we are currently expecting the production to commence towards the mid of Q2
said 27 May 2026 · from the words “Q2 FY27”
we expect our new northern line to be commissioned by September 2026 to capture the peak cold storage cycle
said 2 Aug 2026 · from the words “by September 2026”
going forward, as we have always guided the market, our EBITDA margins from this quarter onwards will be normalized at 10.5% to 11.5%
said 6 Aug 2026 · from the words “Q2 FY27 onwards”
close to 50% or maybe more than 50% of the year's target we should be able to be achieved within these first two quarters
said 6 Aug 2026 · from the words “H1 FY27”
by the end of this quarter I should have some numbers in hand
said 6 Aug 2026 · from the words “Q2 FY27”
The total value of the order is Rs. 48.02 Crores (inclusive of GST) which is to be executed within 90 days.
said 2 Jul 2026 · from the words “Within 90 days” · for Distribution Company · source filing
There are 8 more ORIGEM stores in the pipeline, and they will be operational by September 30, 2026.
said 27 May 2026 · from the words “by September 30, 2026”
For the first half of fiscal 2027, we are looking forward to spend between INR4 crores to INR4.5 crores in marketing expense.
said 30 May 2026 · from the words “H1 FY27”
There are 8 more ORIGEM stores coming up -- 8 to 10 more ORIGEM stores coming up, and they'll be all operational by September 2026.
said 30 May 2026 · from the words “by September 2026”
the National Electricity Policy... is going to be taken up for approval by the Cabinet maybe in the month of August-September
said 31 Jul 2026 · from the words “August-September 2026”
the official production—commercial production— should be by the end of this month, early next month.
said 14 Aug 2026 · from the words “by end of August / early September 2026”
Kheda, Gujarat Facility (PEB) Q2FY27 40,000 ~32,000
said 14 May 2026 · from the words “Q2 FY27”
the Company remains confident of commissioning both plants by Q2FY27
said 14 May 2026 · from the words “Q2 FY27”
Andhra Pradesh (Heavy Steel Structures) Q2FY27 25,000 ~20,000
said 14 May 2026 · from the words “Q2 FY27”
14.32 Crores + GST issue on our Wholly Owned
said 30 Apr 2026 · from the words “7.5 Months” · for Company cannot disclose the name of the Customer on account of confidentiality · source filing
We are right now building the team, and we expect to launch our first fund. I think by end of Q2, again, maybe target about INR1,000 crores, INR1,200 crores or INR1,500 crores in the first fund, some part of it will come in this year.
said 18 May 2026 · from the words “by end of Q2 FY27”
We are expecting that Q2 onwards, actually, we should be seeing a very good demand pull out of the U.S.
said 28 May 2026 · from the words “Q2 FY27”
we have a plan to complete by September, looking to the geographical conditions, looking to the interest of the investors
said 21 May 2026 · from the words “by September 2026”
both the showrooms are targeted to commence operations by quarter 2 of FY27
said 19 May 2026 · from the words “Q2 FY27”
Approximately INR10 crores is the capex incurred for Surat store.
said 17 Aug 2026 · from the words “Q2 FY27”
both the showrooms planned to commence operations in Q2 FY27
said 14 May 2026 · from the words “Q2-FY27”
Surat store date is coming approximately coming on the last week of September.
said 17 Aug 2026 · from the words “last week of September 2026”
Two of these showrooms are scheduled to launch by Q2-FY27
said 14 May 2026 · from the words “Q2-FY27”
2 Significant terms and Repeat order from the existing customer.
said 21 Jul 2026 · from the words “by September 2026” · source filing
Enc.: a/a Saatvik Green Energy Limited (formerly known as Saatvik Green Energy Private Limited) (a Saatvik Group Company)
said 9 Apr 2026 · from the words “Order will be executed by September 2026” · for Received orders from renowned Independent Power producers/EPC Players · source filing
Core Banking: Development complete - moved into customer UAT; Go-live targeted for 30 September 2026
said 30 Jul 2026 · from the words “by 30 September 2026”
we expect a return to the usual run rate from this quarter onwards
said 31 Jul 2026 · from the words “Q2 FY27”
White goods to go-live by Q2 FY27
said 31 Jul 2026 · from the words “Q2 FY27”
we are working on the new LOS platform, which should be in the UAT stage by the end of this quarter. And October to December, we are going to be migrating, which is Perfios platform from Jayam
said 31 Jul 2026 · from the words “Q2 FY27 / Q3 FY27”
we should see some further improvement in the coming quarter
said 31 Jul 2026 · from the words “Q2 FY27”
The balance rights issue money of INR200 crores, INR100 crores from the promoter and the balance INR100 crores from others who participated is expected this quarter, before the end of this quarter
said 31 Jul 2026 · from the words “Q2 FY27”
Nature of order(s) / contract(s) Supply of Bogie Frame Assembly for Non- AC Air Spring Type LHB FIAT Bogie. Awarded by South Eastern Railway
said 15 Apr 2026 · from the words “On or before 13th September, 2026” · for South Eastern Railway · source filing
overall H1, it might not be more than 100 to 120 basis points unless something else happens in the rest of August and September in terms of driving up the prices
said 14 Aug 2026 · from the words “H1 FY27”
compared to Q1, it might be 100 basis points lower
said 14 Aug 2026 · from the words “Q2 FY27”
A date passing is not news anyone reports.
One email a week: what came due, what was filed after, and what is next — with the filing linked on every line.