978 promises made by NSE-listed companies have a date the company named that has not arrived yet. Every one shows the promise in the company's own words, the day it comes due, the phrase that date was read out of, and the filing it came from. River does not say which of these is worth owning — it has no view to offer and will not offer one. It shows the record and asks you.
The promises whose date is nearest, counting from today. Every date here is the one the company named itself.
Single large order. Awarded by Not disclosed due NDA agreements
Comes due 31 Dec 2027 — in about 14 months. From “Approximately December 2027”
Said 3 JUL 2026 · source filing
Quality Power Electrical Equipments Limited has made 3 other dated promises. No update filed since.
Work Order for Operation & Management (O&M) contract as Managed Service Provider (MSP) for managing Haryana StateWideArea Network(HSWAN). Awarded by Haryana State Electronics Development CorporationLimited
Comes due 31 Dec 2027 — in about 14 months. From “31-DEC-27”
Said 2 JUL 2026 · from Haryana State Electronics Development CorporationLimited · source filing
Railtel Corporation Of India Limited has made 53 other dated promises, 4 of which have already come due.
Corporation of India Limited (SECI) for the supply of Solar PV Modules, with an aggregate order value of INR
Comes due 31 Dec 2027 — in about 14 months. From “Order will be executed by December 2027”
Said 15 SEP 2026 · from Solar Energy Corporation of India Limited (SECI) · source filing
Saatvik Green Energy Limited has made 12 other dated promises, 4 of which have already come due.
“Construction of Diversion Road from 4/700 km to 11/500 km of Duduka-Gopalpur-Toparia Road (6 Lane with Service Road) in the District of Sundargarh on EPC Mode". Awarded by Odisha Bridge & Construction Corporation Limited (OB&CC Ltd.)
Comes due 7 Jan 2028 — in about 15 months. From “18 Months”
Said 7 JUL 2026 · from Odisha Bridge & Construction Corporation Limited (OB&CC Ltd.) · source filing
Dilip Buildcon Limited has made 10 other dated promises.
18 (Eighteen) Months from the Date of LOA is to be executed
Comes due ≈ 9 Jan 2028 — in about 15 months. From “18 (Eighteen) Months from the Date of LOA”
The filing counts from a date it names but does not give, so River has measured from the filing date. This day is River's reading, not the company's.
Said 9 JUL 2026 · from Paschim Gujarat Vij Company Limited (PGVCL) · source filing
Viviana Power Tech Limited has made 3 other dated promises.
Based Contract For Conversion of Existing 11 kV HT Line and LT Line Network Including Consumer
Comes due 10 Jan 2028 — in about 15 months. From “18 Months”
Said 10 JUL 2026 · from PASCHIM GUJARAT VIJ COMPANY LTD (PGVCL) · source filing
Advait Energy Transitions Limited has made 5 other dated promises.
The project is scheduled to be executed over a period of 18 months.
Comes due 10 Jan 2028 — in about 15 months. From “18 months”
Said 10 JUL 2026 · from Hyundai Engineering & Construction Co., Ltd · source filing
This is the only dated promise River holds for ION Exchange (India) Limited. No update filed since.
We write to inform you that M/s. Starworth Infrastructure & Construction Limited (SICL) has received a Letter of Intent for the execution of Civil, Structure, Waterproofing and Allied works for Westin Hotel project – Survey No.
Comes due 12 Jan 2028 — in about 15 months. From “20 Months”
Said 12 MAY 2026 · from Innmar Tourism and Hotels Private Limited · source filing
Puravankara Limited has made 4 other dated promises.
RailwaySignaling. Awarded by NorthCentralRailway-Ncr
Comes due 23 Jan 2028 — in about 15 months. From “23-JAN-28”
Said 23 JUL 2026 · from North Central Railway · source filing
Railtel Corporation Of India Limited has made 53 other dated promises, 4 of which have already come due.
We are pleased to inform you that Marine Electricals (India) Limited has received orders amounting to total of Rs 70.86 crores (Approx) Excluding Taxes, the details of the same are mentioned as under: 1.
Comes due 27 Jan 2028 — in about 15 months. From “over a period of 21 months”
Said 27 APR 2026 · from Princeton Digital Group · source filing
Marine Electricals (India) Limited has made 9 other dated promises, 1 of which has already come due.
There is no potential conflict of companies have any interest in interest arising out of this transaction.
Comes due 2 Feb 2028 — in about 15 months. From “Project Delivery Schedule: February 2, 2028”
Said 27 MAR 2026 · from JNK Global Co., Ltd., Korea (“JNK Global”) · source filing
JNK India Limited has made 1 other dated promise.
Bajel Projects Secures a 700 Crore+^ Ultra-Mega Order* from MSETCL for 400/220 kV Substation at Saswad, Pune
Comes due ≈ 13 Feb 2028 — in about 16 months. From “23 Months from the date of issuance of Notification of Award”
The filing counts from a date it names but does not give, so River has measured from the filing date. This day is River's reading, not the company's.
Said 13 MAR 2026 · from MSETCL · source filing
Bajel Projects Limited has made 7 other dated promises.