968 promises made by NSE-listed companies have a date the company named that has not arrived yet. Every one shows the promise in the company's own words, the day it comes due, the phrase that date was read out of, and the filing it came from. River does not say which of these is worth owning — it has no view to offer and will not offer one. It shows the record and asks you.
Ordered by the rupee figure in the filing, largest first, and only promises that stated one. This ranks the figure and not its importance: a large order can matter less to a large company than a small one does to a small company.
Nature of order(s) / contract(s) Provision of nylon mesh on TTC and
Comes due ≈ 30 May 2027 — in about 7 months. From “Within 10 months from the date of issue of Letter of Acceptance”
The filing counts from a date it names but does not give, so River has measured from the filing date. This day is River's reading, not the company's.
Said 30 JUL 2026 · from South Western Railway · source filing
Texmaco Rail & Engineering Limited has made 23 other dated promises, 5 of which have already come due.
The payment to the agency will be made on monthly basis depending upon the actual duration of the support services rendered at NICSI/User Office after availing service.
Comes due 27 Jan 2027 — in about 14 weeks. From “Six Month(s)”
Said 27 JUL 2026 · from Ministry of Electronics and Information Technology through NICSI · source filing
SBC Exports Limited has made 2 other dated promises.
Rig Jindal Pioneer is currently under refurbishment and contract is expected to commence in Q3 FY27.
Comes due 30 Jul 2029 — in about 34 months. From “3 years”
Said 30 JUL 2026 · from Oil & Natural Gas Corporation Ltd · source filing
This is the only dated promise River holds for Jindal Drilling And Industries Limited. No update filed since.
Direct order, participated through Tender. Awarded by Chhattisgarh Environment Conservation Board, Nava Raipur, Atal Nagar
Comes due 5 May 2027 — in about 6 months. From “12 months”
Said 5 MAY 2026 · from Chhattisgarh Environment Conservation Board, Nava Raipur, Atal Nagar · source filing
MIC Electronics Limited has made 1 other dated promise, 1 of which has already come due. No update filed since.
The assignment encompasses the re-design, re-development, testing, commissioning, rollout, security audit, GIGW compliance certification, and comprehensive maintenance of the official CPRI website in a bilingual format.
Comes due 10 Sep 2030 — in about 47 months. From “to be executed; - approximately – 4 years”
Said 10 SEP 2026 · from Central Power Research Institute · source filing
Dev Information Technology Limited has made 3 other dated promises. No update filed since.
The contract value is Rs. 20,64,385.00/- (Rupees Twenty Lakh Sixty-Four Thousand Three Hundred and Eighty-Five Only) plus 18% GST amounting to Rs. 3,71,589.30/- (Three Lakh Seventy-One Thousand Five Hundred and Eighty-Nine and Thirty Paise Only) = Total contract value is Rs.
Comes due 16 Sep 2027 — in about 11 months. From “work shall be completed within 12 months”
Said 16 SEP 2026 · from Larsen & Toubro Limited, Construction · source filing
Univastu India Limited has made 1 other dated promise.
Palwal, Haryana- 121102, India Works: Unit 1, 2 & 3, Village Tatarpur, Dist.
Comes due 31 May 2027 — in about 7 months. From “By May 2027”
Said 5 MAR 2026 · from Due to commercial issue, the Company cannot disclose the name of the Customer · source filing
DEE Development Engineers Limited has made 3 other dated promises.
10 Lakh Metric international entity
Comes due 19 Mar 2028 — in about 17 months. From “18 months extendable with mutual”
Said 19 SEP 2026 · source filing
Refex Industries Limited has made 8 other dated promises.
Remuneration upto Rs. 10,00,000/- (Rupees Ten Lakhs) per month; and - Commission upto @ 2% of the net Profits of the Company.
Comes due 7 Mar 2028 — in about 17 months. From “within a period of 18 months”
Said 7 SEP 2026 · source filing
This is the only dated promise River holds for Commercial Syn Bags Limited.
This engagement will support the operator in expanding its wholesale business ecosystem, ensuring greater operational efficiency, scalability, and accuracy as network complexity increases.
Comes due 21 Aug 2029 — in about 34 months. From “contract spans over a period of 3 years”
Said 21 AUG 2026 · source filing
Subex Limited has made 4 other dated promises.
Storage Systems (BESS) in Gujarat of Gujarat Urja Vikas Nigam Limited(GUVNL) under Tariff-Based competitive bidding (Phase-VIII) with Viability Gap Funding supported through PSDF followed by ERA.
Comes due 30 Sep 2027 — in about 11 months. From “18 Months from date of Battery Energy Storage Purchase Agreement”
Said 31 MAR 2026 · from Gujarat Urja Vikas Nigam Limited (GUVNL) · source filing
Advait Energy Transitions Limited has made 5 other dated promises.
887.20 KM Sewer Network on EPC basis in 306 in brief; Urban Local Bodies (<1 Lakh Population) under
Comes due 11 Apr 2028 — in about 18 months. From “24 months”
Said 11 APR 2026 · from Swachh Maharashtra Mission Directorate · source filing
Enviro Infra Engineers Limited has made 7 other dated promises.