River/ discoverPricing

Promises on the record

What have Indian listed companies promised, and when is it due?

968 promises made by NSE-listed companies have a date the company named that has not arrived yet. Every one shows the promise in the company's own words, the day it comes due, the phrase that date was read out of, and the filing it came from. River does not say which of these is worth owning — it has no view to offer and will not offer one. It shows the record and asks you.

The most recently made promises, newest first. These are the ones nobody else has put a date on yet.

Garden Reach Shipbuilders & Engineers Limitedorder₹1032.07 Crore

Construction and delivery of the vessel. Awarded by Oil and Natural Gas Corporation Limited (ONGC)

Comes due 30 Jul 2030 — in about 46 months. From “Project to be completed within 48 months from the date of NOA”

Said 30 JUL 2026 · from Oil and Natural Gas Corporation Limited (ONGC) · source filing

Garden Reach Shipbuilders & Engineers Limited has made 1 other dated promise.

Astra Microwave Products LimitedorderRs. 2205.23 Crores

This is to inform you that our Company, Astra Microwave Products Limited has received an order for procurement of 122 (One Hundred and Twenty-Two) Nos. of AAAU and 121 (One Hundred and Twenty-One) Interface Frames for Uttam Radar for a total consideration of Rs. 2205.23 Crores in

Comes due 30 Jul 2031 — in about 58 months. From “within 5 years”

Said 30 JUL 2026 · from Hindustan Aeronautics Limited · source filing

Astra Microwave Products Limited has made 1 other dated promise. No update filed since.

HFCLsaid

The expansion of our Optical Fibre manufacturing capacity from 28 million fibre kilometres to 34 million fibre kilometres is progressing well and will be completed by December 2026.

Comes due 31 Dec 2026 — in about 10 weeks. From “by December 2026”

Said 29 JUL 2026

HFCL has made 9 other dated promises, 1 of which has already come due.

ETERNALsaid

we want to take a couple of more quarters and build our thesis more strongly around this, and then we'll share more about this business going forward

Comes due 29 Jan 2027 — in about 14 weeks. From “next two quarters”

Said 29 JUL 2026

This is the only dated promise River holds for ETERNAL. No update filed since.

HFCLsaid

we, to the best of our estimates, can raise our aspirations for FY27 to a revenue growth of 40% and above.

Comes due 31 Mar 2027 — in about 5 months. From “FY27”

Said 29 JUL 2026

HFCL has made 9 other dated promises, 1 of which has already come due.

HFCLsaid

This year, total capex is INR640 crores... Next year will be about INR615 crores, out of which INR325 crores will go to preform and INR175 crores to defence, and INR115 crores balance of INR215 crores would be in data center connectivity solutions.

Comes due 31 Mar 2027 — in about 5 months. From “FY27 and FY28”

Said 29 JUL 2026

HFCL has made 9 other dated promises, 1 of which has already come due.

HFCLsaid

At the beginning of the financial year, we had shared our aspiration of achieving approximately ₹500 crore of Revenue in Defence sector during FY27. Based on the current execution pipeline, customer engagements and order visibility, we remain firmly on track to achieve this objec

Comes due 31 Mar 2027 — in about 5 months. From “FY27”

Said 29 JUL 2026

HFCL has made 9 other dated promises, 1 of which has already come due.

HFCLsaid

Even in the first year of production, which is the current year, we expect a revenue of more than Rs.700 crores with a clear visibility to increase it further multiple folds in subsequent years.

Comes due 31 Mar 2027 — in about 5 months. From “FY27”

Said 29 JUL 2026

HFCL has made 9 other dated promises, 1 of which has already come due.

Hirect Limitedorder

Hirect Secures First Order from the United States for Trac(cid:415)on Motor Assemblies

Comes due 31 Mar 2027 — in about 5 months. From “during FY27”

Said 29 JUL 2026 · source filing

Hirect Limited has made 1 other dated promise.

HFCLsaid

export revenue, I would rather say should remain around 60% or so and 40% would be for local revenue on an overall basis

Comes due 31 Mar 2027 — in about 5 months. From “FY27”

Said 29 JUL 2026

HFCL has made 9 other dated promises, 1 of which has already come due.

HFCLsaid

the full year, we are looking at INR800 crores number, roughly about INR800 crores number. This is the first year of data center connectivity business.

Comes due 31 Mar 2027 — in about 5 months. From “FY27”

Said 29 JUL 2026

HFCL has made 9 other dated promises, 1 of which has already come due.

HFCLsaid

I'm increasing this capacity by 5x. In less than a year's time or let's say a year's time, progressively, my capacity will be 5x more than what it is today.

Comes due 29 Jul 2027 — in about 9 months. From “within one year”

Said 29 JUL 2026

HFCL has made 9 other dated promises, 1 of which has already come due.

A promise here means something a company stated, not something it owes anyone. Schedules get revised, scope changes, and an order extended by agreement is an ordinary commercial event. River records what was said and when it comes due — never whether it was kept. It does not score, rate, rank, recommend or forecast, and it is not a registered investment adviser.