968 promises made by NSE-listed companies have a date the company named that has not arrived yet. Every one shows the promise in the company's own words, the day it comes due, the phrase that date was read out of, and the filing it came from. River does not say which of these is worth owning — it has no view to offer and will not offer one. It shows the record and asks you.

Ordered by the rupee figure in the filing, largest first, and only promises that stated one. This ranks the figure and not its importance: a large order can matter less to a large company than a small one does to a small company.

Prostarm Info Systems Limitedorder6.71 Crores

Supply, Installation and Commissioning of 2MW (AC) Roof Top Solar PV System at various buildings of the plant. Awarded by Steel Authority of India Limited

Comes due 13 Mar 2027 — in about 5 months. From “12 Months”

Said 13 MAR 2026 · from Steel Authority of India Limited · source filing

Prostarm Info Systems Limited has made 2 other dated promises, 1 of which has already come due.

South West Pinnacle Exploration Limitedorder6.64 Crores

The aggregate value of work including GST is ~ 6.64 Crores and the contract is to be completed within a period of 180 days.

Comes due 7 Feb 2027 — in about 15 weeks. From “within a period of 180 days”

Said 11 AUG 2026 · from CMPDI · source filing

South West Pinnacle Exploration Limited has made 3 other dated promises.

Krystal Integrated Services LimitedorderRs. 6.60 Crore

The approximate contract value is Rs. 6.60 Crore excluding all applicable taxes.

Comes due 30 Sep 2027 — in about 11 months. From “12 (Twelve) Months from October 01, 2026 to September 30, 2027”

Said 27 AUG 2026 · from Shree Shyam Mandir Committee · source filing

Krystal Integrated Services Limited has made 8 other dated promises.

Krystal Integrated Services LimitedorderRs. 6,58,35,987

The contract value is Rs. 6,58,35,987 including GST.

Comes due 15 Sep 2027 — in about 11 months. From “1 year from September 16, 2026 to September 15, 2027”

Said 12 SEP 2026 · from Maha Mumbai Metro (M3) Operation Corporation Limited · source filing

Krystal Integrated Services Limited has made 8 other dated promises.

3i Infotech LimitedorderINR 6.32 crore

This is a one-year renewal, received in multiple Purchase Orders totaling INR 6.32 crore, exclusive of applicable taxes.

Comes due 23 Jul 2027 — in about 9 months. From “12 months”

Said 23 JUL 2026 · source filing

3i Infotech Limited has made 13 other dated promises.

Texmaco Rail & Engineering LimitedorderRs. 6.28 crores

Nature of order(s) / contract(s) Provision of Nylon Net, Anti monkey Climbing Device and anti-bird disc over. Awarded by Western Railway

Comes due ≈ 24 Jun 2027 — in about 8 months. From “Within 12 months from the date of issue of Letter of Acceptance”

The filing counts from a date it names but does not give, so River has measured from the filing date. This day is River's reading, not the company's.

Said 24 JUN 2026 · source filing

Texmaco Rail & Engineering Limited has made 23 other dated promises, 5 of which have already come due.

BCPL Railway Infrastructure LimitedorderRs. 6.22 crores

BCPL Railway Infra bags Rs. 6.22 crores work under Howrah division of Eastern Railway

Comes due 23 Mar 2028 — in about 17 months. From “within 18 months”

Said 23 SEP 2026 · source filing

BCPL Railway Infrastructure Limited has made 4 other dated promises. No update filed since.

Magellanic Cloud Limitedorder₹6,16,55,609.34

The total accepted contract value is ₹6,16,55,609.34 (Rupees Six Crore Sixteen Lakh Fifty-Five

Comes due 4 Mar 2027 — in about 4 months. From “12 months from the date of Letter of Acceptance”

Said 4 MAR 2026 · from South East Central Railway, Nagpur Division · source filing

Magellanic Cloud Limited has made 12 other dated promises.

Avantel LimitedorderRs.6.02 Crores

No. 49, Block - 1, Vasavi’s Shalom Sky City, Gambheeram (V), Anandapuram (M), E-City, Raviryal (V), Maheswaram (M), Gachibowli, Serilingampally (M), Ranga Reddy (D), Visakhapatnam - 531 163, Andhra Pradesh.

Comes due 30 Sep 2029 — in about 36 months. From “September 2029”

Said 1 OCT 2026 · from Directorate of Electrical Engineering, Naval Head Quarters, Ministry of Defence · source filing

Avantel Limited has made 13 other dated promises, 2 of which have already come due.

Knack Packaging Limitedorder60 million

Under the new order and renewable of the Contract, the Company will supply packaging material, including PLWPP Bags and Pinch Bottom Bags, aggregating to approximately 60 million bags per annum, having an approximate value of ₹150 Crores per annum.

Comes due 31 Dec 2028 — in about 27 months. From “Contract till December, 2028”

Said 2 OCT 2026 · source filing

This is the only dated promise River holds for Knack Packaging Limited. No update filed since.

South West Pinnacle Exploration Limitedorder5.89 Crores

The aggregate value of work including GST is ~ 5.89 Crores.

Comes due 2 Jan 2027 — in about 10 weeks. From “within a period of 180 days”

Said 6 JUL 2026 · from CMPDI · source filing

South West Pinnacle Exploration Limited has made 3 other dated promises.

3i Infotech LimitedorderRs. 5.66 crores

The engagement involves providing IT Managed Services and onsite technical support resources across various locations covering workplace services, application development support, infrastructure administration and enterprise IT operations.

Comes due 10 Mar 2029 — in about 29 months. From “Three years”

Said 10 MAR 2026 · source filing

3i Infotech Limited has made 13 other dated promises.

A promise here means something a company stated, not something it owes anyone. Schedules get revised, scope changes, and an order extended by agreement is an ordinary commercial event. River records what was said and when it comes due — never whether it was kept. It does not score, rate, rank, recommend or forecast, and it is not a registered investment adviser.

The complete dated inventory · How the record is built