968 promises made by NSE-listed companies have a date the company named that has not arrived yet. Every one shows the promise in the company's own words, the day it comes due, the phrase that date was read out of, and the filing it came from. River does not say which of these is worth owning — it has no view to offer and will not offer one. It shows the record and asks you.
Ordered by the rupee figure in the filing, largest first, and only promises that stated one. This ranks the figure and not its importance: a large order can matter less to a large company than a small one does to a small company.
Paras Defence and Space Technologies Limited (“PARAS”), has received an order from Bharat
Comes due 30 Sep 2027 — in about 11 months. From “Execution to be completed on or before September 2027”
Said 2 JUN 2026 · from Bharat Electronics Limited · source filing
Paras Defence and Space Technologies Limited has made 3 other dated promises.
The total cost of the work at the accepted rates works out to Rs. 526586417.62 (Rupees Fifty-Two Crore Sixty-Five Lakh Eighty-Six Thousand Four Hundred And Seventeen Rupees And Sixty-Two Paise Only)
Comes due 17 Jul 2028 — in about 21 months. From “24 Months”
Said 17 JUL 2026 · from ARSS Infrastructure Projects Limited · source filing
ARSS Infrastructure Projects Limited has made 2 other dated promises, 1 of which has already come due.
Based Contract For Conversion of Existing 11 kV HT Line and LT Line Network Including Consumer
Comes due 10 Jan 2028 — in about 15 months. From “18 Months”
Said 10 JUL 2026 · from PASCHIM GUJARAT VIJ COMPANY LTD (PGVCL) · source filing
Advait Energy Transitions Limited has made 5 other dated promises.
LetterofIntent. Awarded by DirectorIt
Comes due 12 Jan 2027 — in about 11 weeks. From “12-JAN-27”
Said 17 JUN 2026 · source filing
Railtel Corporation Of India Limited has made 52 other dated promises, 4 of which have already come due.
Kalyan Yojana-2 (VKY-2) Scheme / or other scheme of ₹ 51,61,56,375.00/- on July 6, 2026.
Comes due 7 Oct 2027 — in about 12 months. From “15 Months”
Said 7 JUL 2026 · from DAKSHIN GUJARAT VIJ CO. LTD. (DGVCL) · source filing
Advait Energy Transitions Limited has made 5 other dated promises.
Size of Order: Rs. 50,60,87,055/- (Rupees
Comes due ≈ 31 Mar 2027 — in about 5 months. From “12 (Twelve) Months from the Date of LOA”
The filing counts from a date it names but does not give, so River has measured from the filing date. This day is River's reading, not the company's.
Said 31 MAR 2026 · from Paschim Gujarat Vij Company Limited (PGVCL) · source filing
Viviana Power Tech Limited has made 3 other dated promises.
Awarding/Bagging/Receiving of Orders/Contracts
Comes due ≈ 16 Jan 2027 — in about 12 weeks. From “10 Months from the date of issuance of PO”
The filing counts from a date it names but does not give, so River has measured from the filing date. This day is River's reading, not the company's.
Said 16 MAR 2026 · from Tata Power Company Limited · source filing
Bajel Projects Limited has made 7 other dated promises.
With reference to the subject mentioned above, we are pleased to announce that the Company has received purchase orders of Rs.50 crores for manufacturing and export of lab-grown diamonds jewellery.
Comes due 30 Nov 2026 — in 37 days. From “On or before November 30, 2026”
Said 18 AUG 2026 · source filing
Goldiam International Limited has made 11 other dated promises, 4 of which have already come due. No update filed since.
Rs.50 Cr to Rs.100 Rs. 100 Cr to Rs. 200 Cr Rs. 200 Cr to Rs.300 Rs. 300 Cr to Rs.400 Cr Rs. 400 Cr and Cr Cr above
Comes due ≈ 3 Jun 2028 — in about 20 months. From “24 Months from the commencement date”
The filing counts from a date it names but does not give, so River has measured from the filing date. This day is River's reading, not the company's.
Said 3 JUN 2026 · source filing
Bajel Projects Limited has made 7 other dated promises.
Rs.50 Cr to Rs.100 Rs. 100 Cr to Rs. 200 Cr Rs. 200 Cr to Rs.300 Rs. 300 Cr to Rs.400 Cr Rs. 400 Cr and Cr Cr above
Comes due ≈ 12 May 2029 — in about 31 months. From “33 Months from the date of issuance of Notification of Award”
The filing counts from a date it names but does not give, so River has measured from the filing date. This day is River's reading, not the company's.
Said 12 AUG 2026 · source filing
Bajel Projects Limited has made 7 other dated promises.
Rs.50 Cr to Rs.100 Cr Rs. 100 Cr to Rs. 200 Cr Rs. 200 Cr to Rs.300 Cr Rs. 300 Cr to Rs.400 Cr Rs. 400 Cr and above
Comes due ≈ 9 Apr 2028 — in about 18 months. From “18 Months from the date of issuance of Purchase Order”
The filing counts from a date it names but does not give, so River has measured from the filing date. This day is River's reading, not the company's.
Said 9 OCT 2026 · from Tata Power Company Limited · source filing
Bajel Projects Limited has made 7 other dated promises. No update filed since.
Rs.50 Cr to Rs.100 Rs. 100 Cr to Rs. 200 Cr Rs. 200 Cr to Rs.300 Rs. 300 Cr to Rs.400 Cr Rs. 400 Cr and Cr Cr above
Comes due ≈ 13 Feb 2028 — in about 16 months. From “21 Months from the date of issuance of Notification of Award”
The filing counts from a date it names but does not give, so River has measured from the filing date. This day is River's reading, not the company's.
Said 13 MAY 2026 · source filing