Promises on the record

What have Indian listed companies promised, and when is it due?

965 promises made by NSE-listed companies have a date the company named that has not arrived yet. Every one shows the promise in the company's own words, the day it comes due, the phrase that date was read out of, and the filing it came from. River does not say which of these is worth owning — it has no view to offer and will not offer one. It shows the record and asks you.

The promises whose date is nearest, counting from today. Every date here is the one the company named itself.

Bajel Projects LimitedorderRs.50 Cr

Awarding/Bagging/Receiving of Orders/Contracts

Comes due ≈ 16 Jan 2027 — in about 12 weeks. From “10 Months from the date of issuance of PO”

The filing counts from a date it names but does not give, so River has measured from the filing date. This day is River's reading, not the company's.

Said 16 MAR 2026 · from Tata Power Company Limited · source filing

Bajel Projects Limited has made 7 other dated promises.

Magellanic Cloud LimitedorderRs 29.13 Crore

Magellanic Cloud Limited has informed the Exchange regarding a press release dated October 16, 2026, titled "Magellanic Cloud Limited's Wholly Owned Subsidiary Provigil Surveillance Limited, Receives Purchase Order for an order worth Rs 29.13 Crore from Northern Railway Moradabad

Comes due 16 Jan 2027 — in about 12 weeks. From “to be completed in 3 Months”

Said 16 OCT 2026 · from Northern Railway Moradabad Division · source filing

Magellanic Cloud Limited has made 12 other dated promises. No update filed since.

Servotech Renewable Power System Limitedorder

Plaza, 5th Floor, Plot no. C/1 G Block, BandraKurla Complex, Bandra (E) Mumbai – 400051 Trading Symbol: SERVOTECH

Comes due 16 Jan 2027 — in about 12 weeks. From “Within 06 months”

Said 16 JUL 2026 · from UPSRLM, Rural Development Department Uttar Pradesh · source filing

Servotech Renewable Power System Limited has made 1 other dated promise. No update filed since.

Railtel Corporation Of India LimitedorderRs. 48,37,96,563/-

LetterofAward. Awarded by North Bihar Power Distribution Company Ltd

Comes due 17 Jan 2027 — in about 12 weeks. From “17-JAN-27”

Said 19 MAR 2026 · from North Bihar Power Distribution Company Ltd · source filing

Railtel Corporation Of India Limited has made 51 other dated promises, 4 of which have already come due.

Sanginita Chemicals Limitedorder

SANGINITA CHEMICALS LTD. l{, (Erstwhile known as Sanginita Chemicals Pvt. Ltd.)

Comes due 17 Jan 2027 — in about 12 weeks. From “within 150 days”

Said 20 AUG 2026 · source filing

This is the only dated promise River holds for Sanginita Chemicals Limited. No update filed since.

Zodiac Energy Limitedorder₹30,85,29,808

INR ₹30,85,29,808 (Thirty Crore Eighty-Five Lakh TwentyNine Thousand Eight Hundred Eight Rupees Only) 8.

Comes due ≈ 22 Jan 2027 — in about 13 weeks. From “Within 9 months Approximately subject to terms of LOI”

The filing counts from a date it names but does not give, so River has measured from the filing date. This day is River's reading, not the company's.

Said 22 APR 2026 · source filing

Zodiac Energy Limited has made 1 other dated promise.

Ceigall India LimitedorderRs. 298 crores

Notably, the Company has received EPC contracts from Purvah Green Power Private Limited, aggregating approximately Rs. 298 crores.

Comes due 24 Jan 2027 — in about 13 weeks. From “10 months constructions period”

Said 24 MAR 2026 · from Purvah Green Power Private Limited · source filing

Ceigall India Limited has made 13 other dated promises, 1 of which has already come due.

RMC Switchgears Limitedorder₹ 5,01,72,500 -

Requirements) Regulations, 2015 – Receipt of Letter of Award

Comes due 24 Jan 2027 — in about 13 weeks. From “6 Months”

Said 24 JUL 2026 · from Genus Power Infrastructures Limited · source filing

RMC Switchgears Limited has made 4 other dated promises, 1 of which has already come due.

SBC Exports Limitedorder₹ 52,19,862/-

 The payment to the agency will be made on monthly basis depending upon the actual duration of the support services rendered at NICSI/User Office after availing service.

Comes due 27 Jan 2027 — in about 14 weeks. From “Six Month(s)”

Said 27 JUL 2026 · from Ministry of Electronics and Information Technology through NICSI · source filing

SBC Exports Limited has made 2 other dated promises.

Marine Electricals (India) LimitedorderRs 250.78 crores

We are pleased to inform you that Marine Electricals (India) Limited has awarded orders totaling Rs 250.78 crores (Approx) Excluding Taxes, the details of the same are mentioned as under: 1.

Comes due 28 Jan 2027 — in about 14 weeks. From “over a period of 4 months”

Said 28 SEP 2026 · from Digital Edge DC · source filing

Marine Electricals (India) Limited has made 9 other dated promises, 1 of which has already come due. No update filed since.

ETERNALsaid

we want to take a couple of more quarters and build our thesis more strongly around this, and then we'll share more about this business going forward

Comes due 29 Jan 2027 — in about 14 weeks. From “next two quarters”

Said 29 JUL 2026

This is the only dated promise River holds for ETERNAL. No update filed since.

Diamond Power Infrastructure Limitedorder₹ 61,03,55,000/-

11, 2023 (as amended), we wish to inform the Exchange that the Company has received a Letter of Intent dated 12

Comes due 31 Jan 2027 — in about 14 weeks. From “By January 2027”

Said 12 AUG 2026 · from Purvanchal Vidyut Vitran Nigam Limited (PuVVNL), a power · source filing

Diamond Power Infrastructure Limited has made 5 other dated promises, 1 of which has already come due.

A promise here means something a company stated, not something it owes anyone. Schedules get revised, scope changes, and an order extended by agreement is an ordinary commercial event. River records what was said and when it comes due — never whether it was kept. It does not score, rate, rank, recommend or forecast, and it is not a registered investment adviser.