  "source_name": "River",
  "canonical": "https://withriver.in/won/ASHOKA",
  "description": "Orders Ashoka Buildcon Limited (ASHOKA) announced to the National Stock Exchange of India, newest first, each linked to the filing it came from.",
  "method": "Corporate announcements filed with the National Stock Exchange of India are read daily across all listed companies. Announcements where a company reports winning work are kept; announcements using 'order' in its legal sense (tax demands, tribunal and regulatory orders) are excluded by rule. Where a filing attaches a document, the value, counterparty and execution period are taken from the company's own words in that document. Restatements of a cumulative order book are flagged and excluded from all totals. Foreign-currency values are counted but not converted. River does not rate, rank or forecast.",
  "license": "Free to quote and reproduce with attribution to River (withriver.in). Underlying documents are public filings of the National Stock Exchange of India.",
  "attribution": "River, \"What Ashoka Buildcon Limited said it won\", compiled from corporate filings, https://withriver.in/won/ASHOKA",
  "generated_at": "2026-10-22T08:44:54.898Z",
  "company": {
    "symbol": "ASHOKA",
    "name": "Ashoka Buildcon Limited",
    "exchange": "NSE"
  },
  "count": 6,
  "earliest_on": "2026-02-21",
  "latest_on": "2026-10-09",
  "orders": [
    {
      "announced_on": "2026-10-09",
      "statement": "Further to apprise that the Company has received Letter of Acceptance for the said Project.",
      "value_as_filed": null,
      "value_inr_crore": null,
      "currency": null,
      "counterparty": "North Eastern Railway",
      "execution_window": "Completion Period: 24 months from date of commencement",
      "source": "https://nsearchives.nseindia.com/corporate/ASHOKA_09102026174804_507_ABL_BSE_NSE_NER_LoA_091026.pdf"
    },
    {
      "announced_on": "2026-08-29",
      "statement": "Package-3: Supply, Erection, Testing & Commissioning of Electro Mechanical (E&M) System comprising of 33/11kv & 11/0.433kv GIS Substations, HT & LT Cables, DG Sets, Lighting, Ups System, Ventilation Systems & Fire Fighting Systems and other associated works for Tunnel T-13, T-14, T-15 & T-16 under package E-4 of…",
      "value_as_filed": "Rs.25.51 Crore",
      "value_inr_crore": 25.51,
      "currency": "INR",
      "counterparty": "Rail Vikas Nigam Limited, vide LOA dated August 28, 2026",
      "execution_window": "Completion Period: 30 months from date of commencement",
      "source": "https://nsearchives.nseindia.com/corporate/ASHOKA_29082026101205_501_ABL_BSE_NSE_RVNL_LoA_290826.pdf"
    },
    {
      "announced_on": "2026-08-13",
      "statement": "Performance Bank Guarantee of Rs.16.70 Crore within 10 days of issuance of LoI date",
      "value_as_filed": "Rs.16.70 Crore",
      "value_inr_crore": 16.7,
      "currency": "INR",
      "counterparty": "REC Power Development and Consultancy Limited, vide LOI dated August 13, 2026",
      "execution_window": "Completion Period: 24 months Operation & Maintenance Period 35 years",
      "source": "https://nsearchives.nseindia.com/corporate/ASHOKA_13082026153301_500_ABL_BSE_NSE_Sakoli_LoI_130826.pdf"
    },
    {
      "announced_on": "2026-06-13",
      "statement": "The accepted amount of premium to be paid for the Project is Rs.112.40 Crore.",
      "value_as_filed": "Rs.112.40 Crore",
      "value_inr_crore": 112.4,
      "currency": "INR",
      "counterparty": "Chhattishgarh State Industrial Development Corporation Limited (CSIDC)",
      "execution_window": "Lease Period of 30 years, extendable up to 90 years",
      "source": "https://nsearchives.nseindia.com/corporate/ASHOKA_13062026125129_490_ABL_BSE_NSE_Gems_Park_LoA_13062026.pdf"
    },
    {
      "announced_on": "2026-04-24",
      "statement": "Further to update that the Company has received Letter of Contract Acceptance for the said Project.",
      "value_as_filed": null,
      "value_inr_crore": null,
      "currency": null,
      "counterparty": "Ministry of Energy and Water the Republic of Angola (“the Authority”)",
      "execution_window": "24 months",
      "source": "https://nsearchives.nseindia.com/corporate/ASHOKA_24042026125704_485_ABL_BSE_NSE_Angola_LOA_24042026.pdf"
    },
    {
      "announced_on": "2026-02-21",
      "statement": "Selection of a Managed Service Provider for Modernization of Offices under Inspector General of Registration and Controller of Stamps (IGR), under the Govt. of Maharashtra’ (“Project”) This is to apprise that the Consortium has received Letter of Intent (LOI) for the said Project.",
      "value_as_filed": "9.18 Crore",
      "value_inr_crore": 9.18,
      "currency": "INR",
      "counterparty": null,
      "execution_window": "March 19, 2032",
      "source": "https://nsearchives.nseindia.com/corporate/ASHOKA_21022026153632_467_ABL_BSE_NSE_IGR_LoI_210226.pdf"
    }
  ]
}